Water Authority Eyes 2028 Finish for North Fork Pipeline's First Phase
The chosen Main Road route still faces a Riverhead permit fight and pending approvals

The Suffolk County Water Authority adopted a formal findings statement on Nov. 19 for a new North Fork water main along Cross River Drive, then along Main Road, concluding that the work's benefits outweigh its expected environmental effects.
The first phase would carry a 24-inch transmission line about 7 miles. It would start near the Flanders Road intersection in the Riverside-Flanders area, pass under the Peconic River next to the bridge on Cross River Drive, and tie into an existing authority main near the Southold line in Laurel. A one-story booster station would sit on a small authority-owned lot in Aquebogue, at the southeast corner where Main Road meets Cross River Drive. The board dropped an earlier alignment that followed Northville Turnpike and Sound Avenue. The chosen course is about a mile shorter and sits at lower elevations. It requires a single booster station.
The findings close the authority's state environmental review and authorize the chief executive to file the remaining applications. Officials expect first-phase construction to last under a year once final approvals are in hand, though the start and finish dates still depend on those permits. The authority's project page lists completion by 2028. State highway and wetlands approvals and a federal permit for the river crossing have not been issued.
The line is meant to move water from the authority's South Shore system into Southold, where summer demand already outruns what local wells can pump. The authority serves about 9,500 customers on the North Fork. Officials say most of the wells draw from a shallow aquifer exposed to contamination and to saltwater if pumping stays high. The environmental study calls for ending regular service at eight Southold wells and cutting withdrawals at nine others once the new main is running.
Riverhead would host much of the trench work and the booster station but would not receive service from the line. In a unanimous Oct. 6 vote, the Town Board said the town would not receive that service and held that the project must follow the town's zoning and planning rules. Those rules, the town says, include special-permit and site-plan review for the booster station, plus road-opening and wetlands permits and utility easements. The authority argues it is exempt from that local review as a public authority carrying out a core government function, and notes that the main would not hook up customers inside the Riverhead Water District.
The authority sued the town on Feb. 6 in Suffolk's State Supreme Court, challenging an earlier town finding from October 2025 on the original Sound Avenue route. On Oct. 29, after the town applied the same local-review demand to the Main Road path, the water authority's board voted to have its lawyers open a further case or expand the one already on file. The February lawsuit was still pending when that vote was taken.
Construction measures in the findings include a daily website of work locations and detours and a construction manager to oversee the job, with steps to keep access open for neighboring homes and businesses. Crews are to avoid opening roads in high-traffic stretches when summer and fall traffic is heaviest, where that is practical. Before crews get to Aquebogue Elementary School, the authority is to coordinate a traffic plan covering arrival and dismissal, bus routes, parent pickup, and pedestrian paths.
The first phase of the Main Road option carries a contract estimate of about $20 million in the July study. The findings state that the course is costlier to build than the Sound Avenue option and that it passes more driveways and businesses. The board selected it for the shorter distance and because it needs only one booster station. A possible later extension of about 6 miles, from East Marion into Orient, is covered in the same review as long-range planning for homes that now rely on private wells in a county health priority area. That work would depend on later demand and funding.
At the Oct. 29 meeting, Chairman Charles A. Lefkowitz called the pipeline the biggest infrastructure job in the authority's 75 years of operations, which began in June 1951. Construction of the first phase still waits on the remaining permits and on the court fight over Riverhead's local rules. The 2028 completion date on the project page depends on that sequence.
You Might Also Be Interested In

State Grant Will Reopen a Closed Calverton Soccer Field

State Moves to Reopen Western Long Island Sound to Commercial Striped Bass Fishing

Suffolk Legislature Votes to Open Peconic and Gardiner's Bays to Seaweed Farming